Due to safety concerns, Central Coast Council issued a demolition order for the removal of the boatshed and jetties at the former Empire Bay Marina.
The demolition order relates to the aboveground structures for the boatshed and associated jetties only.
The former Empire Bay Marina site is significantly contaminated, and engineering advice warned the building was unstable and at risk of collapse during site remediation works.
The boatshed was demolished in accordance with the demolition order.
The boatshed was removed to allow the safe removal of the underground fuel system and the remediation of soil contamination at the site to ensure it is safe for the community and the environment.
Our intention is to restore the site to usable public open space.
Latest project update
Site remediation
The remediation of the site is complex and has required staged work to address the historical contamination from long-term marina operations.
Contamination investigations to understand the condition of the site and the risks from contamination have now been completed.
We are now preparing the final stage of remediation and foreshore rehabilitation.
Stage 1a: Demolition
Crown Lands complied with local council’s demolition order by removing the unsafe boatshed and jetties. The demolition order did not require the removal of the underground fuel tanks or pylons.
Stage 1b: Fuel infrastructure removal
A Development Application (DA), supported by a Remedial Action Plan (RAP), was approved by local council for the removal of the slipway, underground fuel tanks and associated equipment. This work was completed in April - May 2024.
Stage 2a: Contamination investigation
Comprehensive contamination testing, including a Detailed Site Investigation (DSI), Underground Petroleum Storage System (UPSS) Validation Report, Supplementary Contamination Investigation (SCI), Sediment Delineation Investigation (SDI), and Supplementary Soil and Groundwater Assessment has been finalised.
A Human Health and Ecological Risk Assessment Human (PDF, 232 KB) – external PDF may not meet NSW Government accessibility standards), to determine the full remediation requirements for the site has also been completed.
Stage 2b: Remediation planning and approvals
A Remedial Action Plan (RAP) is being prepared to guide the final site remediation and foreshore stabilisation. This includes measures to manage in-water works of priority areas whilst minimising disturbance of contaminated sediments.
Crown Lands is also preparing a DA for:
- Remaining remediation works such as localised sand capping
- Seawall and foreshore rehabilitation
- Management of remaining pylons
- Landscaping
- Heritage memorialisation.
Crown Lands will consult with the community on options for memorialising the boatshed prior to lodging the DA.
Crown Lands anticipates the DA will be lodged in June 2026.
Stage 3: Remediation works
Subject to development consent.
Voluntary Management Proposal approved
A Voluntary Management Proposal (VMP) for the site has been approved by the NSW Environment Protection Authority (NSW EPA).
The VMP outlines how site contamination will be managed.
The VMP was developed in consultation with the NSW EPA, an independent accredited auditor and environmental consultants. The VMP can be found below. Crown Lands is consulting with the NSW EPA on amendments to the VMP timeframes.
Background
In late 2020, Crown Lands revoked the Empire Bay Marina operator’s licence due to significant and ongoing breaches of the licence conditions, and the licence holder’s failure to rectify the issues despite repeated requests.
Building condition and structural engineer’s reports from 2020 (PDF, 15.9 MB) and 2022 (PDF, 8.8 MB) found the boatshed had major structural defects, was structurally unsound and unsafe, and did not comply with the Building Code of Australia. The jetties were in poor condition and unsafe, the underground fuel tanks had not been appropriately decommissioned, and lead-based paint was peeling off external walls.
Crown Lands commissioned a Detailed Site Investigation (DSI) (PDF, 17.3 MB) July 2021. The DSI found higher than acceptable levels of contamination at the former marina, from sources likely including fuel, oil, lead based paint, asbestos and antifouling chemicals.
In May 2022, The NSW EPA declared the site significantly contaminated under the Contaminated Land Management Act 1997.
In July 2023, SafeWork NSW issued an Improvement Notice. The notice states that the underground fuel tanks and associated equipment must be removed by 31 March 2024. This includes all fuel lines and vents.
As the boat shed was listed as an item of local heritage significance in the Central Coast Local Environmental Plan 2022, Crown Lands commissioned Eureka Heritage to prepare a Statement of Heritage Impact (PDF, 12 KB).
The report found:
- Historic local shipbuilding did not occur at the site.
- There is a likely association between the boatshed and ferries making deliveries for the Davis and Settree Store from the 1920s, however no historical references substantiated this.
- The boatshed is a foreshore landmark but its modified structure and additions, including its jetties, obscured its historical context and significance.
- There was an opportunity to salvage boatshed items of heritage value including double sliding doors and double timber doors from about 1925 and signage from about 1970.
- Salvageable items are limited due to contamination, degradation and non-heritage materials that have been used in repairs or modifications.
As well as contamination and structural issues, other constraints on the former marina include its location in a now established residential area with no legal vehicle access, parking or sewerage.
Alternative marina facilities are available in Brisbane Water at nearby locations including Koolewong, Booker Bay and Killcare.
Related information
- Empire Bay Marina and Boatshed – September 2025 (PDF, 91 KB)
- Empire Bay Marina and Boatshed - May 2025 (PDF, 118 KB)
- Empire Bay Marina and Boatshed - December 2024 (PDF, 189 KB)
- Empire Bay Marina and Boatshed - April 2024 (PDF, 168 KB)
- Empire Bay Marina and Boatshed - February 2024 (PDF, 168 KB)
- Empire Bay Marina and Boatshed - October 2023 (PDF, 62.38 KB)
- Empire Bay Marina and Boatshed - Frequently asked questions - September 2023 (PDF, 102 KB)
- Empire Bay Marina and Boatshed - July 2023 (PDF, 82 KB)
- Empire Bay Marina and Boatshed – Frequently asked questions – November 2022 (PDF, 170 KB)
- Empire Bay Marina and Boatshed – August 2022 (PDF, 167 KB)
- Empire Bay Marina and Boatshed – May 2022 (PDF, 161 KB)
- Empire Bay Marina and Boatshed – December 2021 (PDF, 80 KB)
- Empire Bay Marina and Boatshed – September-October 2021 (PDF, 118 KB)
- Empire Bay Marina and Boatshed – updated July-August 2021 (PDF, 154 KB)
- Empire Bay Marina and Boatshed – updated June 2021 (PDF, 144 KB)
- Empire Bay Marina Human Health and Ecological Risk Assessment (PDF, 8.5 MB)
- Human Health and Ecological Risk Assessment – Auditor's report (PDF, 232 KB)
- Northrop Structural Report – November 2022 (PDF, 8.8 MB)
- VMP under the Contaminated Land Management Act 1997 (PDF, 575 KB)
- Addendum to structural report for Empire Bay marine structure (PDF, 688 KB)
- ERM - Empire Bay Marina Sediment Delineation Investigation (PDF, 3.1 MB)