We are repairing the spillway channel to improve dam safety and resilience during future high-flow events.
Location
Barry Road, Hanging Rock
Dates
September 2026 to November 2026
Work times
Weekdays 7 am to 5 pm
Key points
Works will include:
- regrading of the channel
- reconstruction of damaged spillway sections
- installation of a concrete lining system
- erosion and sediment controls
- rehabilitation and revegetation.
Impacts
During works, there may be:
- temporary fencing in place and, for safety, restricted access to the immediate site
- short term noise associated with construction activities
- temporary traffic management.
We apologise for any inconvenience this may cause and will provide advance notice where possible.