Crown reserve remediation works at Bulahdelah

Projects

Remediation of the Crown reserve is complete. The project included removing contaminated materials and unused infrastructure and restoring the site for future use.

Summary

nswg_pictogram_fill_map-marker_blue01.svg

Location

Crown reserve off Crawford Street, Bulahdelah

nswg_pictogram_fill_calendar_blue01.svg

Dates

May to September 2025

nswg_pictogram_fill_accounting-bill-stack_blue01.svg

Project investment

$385,000

Key outcomes

  • Removal of contaminated soil to prevent environmental impacts and protect the community.
  • Demolition of damaged wharf impacted by flooding events and redundant refuelling infrastructure including storage fuel tank, fuel shed, underground fuel lines, fuel dispenser and winch storage shed.
  • Bank stabilisation work including 390 native saplings planted along the riverbank.
  • Improved site safety and alignment with RU5 – Village zoning which allows for recreational, tourist or commercial land uses.
  • Minimised disruption to the local community through managed construction practices for noise, dust and vibration.